1WorldSync Obligations
The work would be to change the existing Salsify to SyncPDI integration to be expanded to include Canada products and French language support (handful of new properties to be mapped/setup). Today, the integration is only for “topping off” USA products.
Client Obligations
Responsibilities
- I. Supplier Responsibilities:
- 3.A.I.1 Inform KHC of their progress and any issues encountered during the exécution of the services.
- II. Kraft Heinz Responsibilities:
- 3.A.II.1 All hardware/software will be provided by Kraft Heinz (KHC)
- 3.A.II.2 KHC will supply access to all required systems to perform the work.
Assumptions
- 3.B.1 Work will be conducted remotely.
- 3.B.2 Changes in scope and/or increased complexity may delay the implementation of this SOW and
increase costs. Any request for additional assistance beyond what has been allocated and specifically
identified in the services description will be subject to the Changes to Statement of Work Process.
- 3.B.3 KHC will provide the data and information to the project team in an accurate, complete and timely
manner.
- 3.B.4 KHC will make the required resource(s) available to the delivery team for the duration of this
SOW
Scope/Tasks
- Finalize requirements: Complete review of a sample updated Salsify import file data.
Finalize the mapping of fields from the Salsify file to applicable GDSN attributes.
- Update Sync/PDI UI: Add and display additional imported Salsify fields (e.g.French language fields)
- Develop and test updated integration file import: Update the import process for the updated Salsify file and map to applicable GDSN attributes
- Deploy to production: Deploy updates and import to production Sync/PDI and monitor first few imports closely; Ensure new fields flow correctly to target market Canada recipients